Hide Activities in Asta

2 replies [Last post]
Bill Joshaf
User offline. Last seen 15 years 44 weeks ago. Offline
Joined: 26 Jun 2005
Posts: 33
Groups: None
Any Asta expert can tell me the tips that how to hide the specific activities in Asta? I used these options to hide the specific activities.
Hide and show the toolbar and Mark for hiding
but no result.
Any idea?


Replies

Bill Joshaf
User offline. Last seen 15 years 44 weeks ago. Offline
Joined: 26 Jun 2005
Posts: 33
Groups: None
Hi Mike
Thanks for your prompt response. Its really good tip.
Mike Testro
User offline. Last seen 48 weeks 1 hour ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Bill

In version 10 select the bar and right click on the task for the task drop down.

Left click on the "Mark for Hiding" option.

Repeat for all other tasks.

In the Format drop down click Hide Marked Items.

The marked tasks disapear.

Best regards

Mike Testro