Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Current view progress only calculated and not hidden

1 reply [Last post]
Bernie Kurland
User offline. Last seen 13 years 30 weeks ago. Offline
Joined: 18 Aug 2010
Posts: 2
Groups: None
Has anyone tried this
I want to calcilate current view progress and not to include any activity progress not in current view
This will apply to activities using a filter whether they have progress or not but to exclude typically "by others" for example

Bernie

Replies

Mike Testro
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Bernie

Welcome to Planning Planet

You can enter progress on a filtered view on all or selected tasks and it will be effective when you drop the filter.

Make sure you tick the Link Around Completed Tasks when doing the excercise.

Best regards

Mike Testro