How many id’s for each activity?

2 replies [Last post]
Bijaya Bajracharya
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 25 Feb 2005
Posts: 175
Groups: None
I was amazed to find a number of confusing data (tokens). I was trying to find activity id and found following four:
Task id
Bar id
Id
Unique Task ID

Can someone explain what these are?

Replies

Bijaya Bajracharya
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 25 Feb 2005
Posts: 175
Groups: None
Thank you for explaining. Graphics based and hence I had a feeling that Power Project would be more user friendly. But....
Andrew Pearce
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 11 Jun 2001
Posts: 175
First of all you need to understand that power project is a graphically based programme.

You have bars Which are single activities on a gant chart line. As you add activities in your programme PP gives each one a line number (bar ID) at the same time PP allocates a unique ID to this bar, the unique ID does not change whereas the bar (or line no) changes if you add or move the bar.

In PP you have the ability to split bars into tasks and the same numbering logic applies to the tasks.

A way of checking this is to add columns to the spreadsheet for each token.