Planning & Scheduling with ASTA Powerproject

Assistant Planner or Planning Engineer, Laing O'Rourke, A590 High & Low Newton Bypass

START Date: 
January, 2007
END Date: 
August, 2007

Planning Engineer, Laing O’Rourke, Cumbria, UK, Jan 2007 – Aug 2007

Project: A590 High & Low Newton Bypass – Highways Agency – £26m

 

Construction of a 3.8km dual carriageway situated within the Lake District National Park.

 

Roles and responsibilities:

  • Weekly project planning.
  • 6 weekly project schedules.
  • Material wastage reporting.
  • Timesheet coding and earned value management.
  • Creation of output information.
Experience Hours (Planning & Scheduling): 
700
Experience Hours (Cost Management): 
600

Director, Willmer Limited, S Curve software

START Date: 
January, 2014

Willmer Limited is a UK  based company that offers planning and training services for any company involved in projects. The founders have a vast amount of experience of implementing, training and delivering planning and scheduling services to the construction, rail and engineering industries. Additionally we have worked with Finance, IT and Pharmaceutical companies. 

International Sales & Marketing Assistant, Asta Development plc, none

START Date: 
September, 2007

Assisting Internatinal Sales manager to develop sales via our Channel Partners

Site Planner, Vinci Construction UK Limited, Student Accomodation

START Date: 
January, 2012

Progress Reporting; short term programms; Early tender involvement; producing 3D model in Google Sketchup / Adobe Special Effects to portray programme sequencing / visualisation;

Quantity Surveyor/Contracts Manager/Project Planner, Various Companies, Various

START Date: 
February, 1995

I stated as a Quantity Surveying at a company in Cape Town, South Africa. I then moved into the site management sector & became Planner & ended up as a Contracts Manager. When i left South Africa, I joined an envelope company as a Project Planner.

Construction Planner, MACE GROUP LIMITED, New Builds/Refurbishments

START Date: 
September, 2006

Construction Planner for Main Contractor, MACE GROUP LIMITED

Progress Reporting, Planning & Scheduling with ASTA Powerproject

Project Planner, JFM Projects, Bankside 2&3, Crystal Palace NSC, ExCel Phase 2, One New Change, Project HAL

START Date: 
June, 2006
END Date: 
October, 2009

Projects worked:

1) Project HAL
2) Crystal Palace NSC
3) The Savoy Hotel
4) One New Change
5) Bankside 2&3
6) ExCel - Phase 2

Assistant Planner & Planner, Axima Suez, A variety of tenders and site based projects

START Date: 
June, 2005
END Date: 
June, 2006

Training year and mostly tender programmes production; my role was to support the lead planner as well as visit various sites for progress reporting purposes.

Market Place

For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes
Syndicate content