P6 Planning and Scheduling; Progress Monitoring

Planner/Scheduler, OC/CH2M Hill, Plant construction include civil and MEP works

START Date: 
October, 2011
END Date: 
July, 2012

provide Planning, programming, progress monitoring and coordination to both client and construction management team for a plant construction project

Planning Engineer, Bombardier, SSL

START Date: 
April, 2011

Schedule emerging work during the realisation phase of the project

Estimate anticipated work during this phase

Provide a forecast each month of the remaining work

Monitor progress through one to one meetings with lead engineers and daily visulisation meetings

Provide data for KPIs

Planning Engineer, Bombardier, SSL

START Date: 
April, 2011

Schedule emerging work during the realisation phase of the project

Estimate anticipated work during this phase

Provide a forecast each month of the remaining work

Monitor progress through one to one meetings with lead engineers and daily visulisation meetings

Provide data for KPIs

Planning Engineer, Bombardier, SSL

START Date: 
April, 2011
END Date: 
July, 2012

Schedule emerging work during the realisation phase of the project

Estimate anticipated work during this phase

Provide a forecast each month of the remaining work

Monitor progress through one to one meetings with lead engineers and daily visulisation meetings

Provide data for KPIs

Planning Engineer, Bombardier, SSL

START Date: 
April, 2011
END Date: 
July, 2012

Schedule emerging work during the realisation phase of the project

Estimate anticipated work during this phase

Provide a forecast each month of the remaining work

Monitor progress through one to one meetings with lead engineers and daily visulisation meetings

Provide data for KPIs

Planning Engineer - Project & Claims, Al Nekhreh Contracting Co., 24 & 14 Residential villas, 2B+G+9P+41 Baygate Commercial Tower, 5B+G+4P+23 Capital Tower, AAM Tower, Al Faris Hotel apartments, B+G+M+28 Emirates Staff Accomm., IMPZ Residential Tower, IRI

START Date: 
June, 2008
END Date: 
April, 2013

•     Primarily   responsible   for   preparing,   updating,   monitoring   and  revising   the  Construction   Master Programme according to the project schedule needs.

•     Costloading and resource loading of the Construction Master Programme and monitored the same.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes