Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Claims Preparation

Claims Preparation, Evans & Peck, Power Station Construction for Endel

START Date: 
November, 2007
END Date: 
December, 2007

Preparation of Extension of Time Claim for Contractor constructing two 50MW Power Stations in New Caledonia

Claims Consultant, Freelance Consultant, Alba Bauxite Treatment aluminium smelter and associated works

START Date: 
January, 2005
END Date: 
May, 2005

Preparation and defence of Claims and References for International Arbitration. Involved in large scale engineering projects in the Middle East, Japan and Malta. Advising on strategy, dispute process and risk assessment. Also providing specific and innovative disruption and loss of productivity formulae and demonstration.  

Preparation of EOT Claim for Bahraini Steelwork fabricator and constructor against Main Contractor

Claims Consultant, Cyril Sweett, Jubilee Line Pumps & Sumps & Various Projects

START Date: 
March, 2005
END Date: 
May, 2007

Head of Legal Support Services Scotland

Establishing and Developing Business. Contract advice and Claim Preparation on AUD25M Rail Dispute. Quantum Expert Witness Testimony on a number of projects. Seminars and Workshops on various forms of Construction Contracts. Preparation and defence of various claims including £5M House Builder Arbitration.

Planning Manager, Postlewhite Project Planning, Various Construction Projects

START Date: 
November, 2001
END Date: 
March, 2003

Worked on various projects as Planning Manager, Cliams consultant and Programme Manager.

Market Place