Delay Analysis / Time Impact Analysis / EOT Claims Coordination of Contractors Programmes Monitor Project Works to ensure Completion of Target Dates Revise

Forensic Planner / Delay Analyst, Lend Lease, Cape Lambert Rail Expansion Earthworks

START Date: 
June, 2013
END Date: 
February, 2014

Forensic Planner(3 months full time & as required through Mediation process), 6/2013 to 2/2014

Defense and implementation support for “Extension of Time” claim

Selected Accomplishments:

Introduction of Bill of quantities values of various types of earthworks values from estimates into various Primavera updated schedules.

Conversion of various earthworks units of measure into “Mass Haul” values and re-introduce these values into various updated schedules.

Experience Hours (Planning & Scheduling): 
100
Experience Hours (Cost Management): 
350
Experience Hours (Forensic Analysis): 
1000

Framework Coordinator = Senior Planning Engineer, ASCO Consulting Engineers/CDM Smith, Abu Hamour (Musaimeer) Surface & Ground water Drainage Tunnel Phase 1,

START Date: 
January, 2015

The project involves design and construction of 9.5 kilometres long and 3.7 meters pre-cast segment lined inside diameter, storm water conveyance tunnel. The project also includes 24 deep access shafts and their adit-tunnel connections for Qatar Public Work Authority (ASHGHAL).

Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Forensic Analysis): 
1000

Framework Coordinator = Senior Planning Engineer, ASCO Consulting Engineers/CDM Smith, Abu Hamour (Musaimeer) Surface & Ground water Drainage Tunnel Phase 1

START Date: 
January, 2015
END Date: 
August, 2016

Continues Employment contract with ASCO Qatar till present.

Project: Abu Hamour Surface & Ground Water Drainage Tunnel Phase 1, was design and construction of 9.5 kilometre long and 3.7 meter pre-cast segment lined inside diameter, storm water conveyance tunnel. The project also included 24 deep access shafts and their adit-tunnel connections for Qatar Public Work Authority (ASHGHAL).

Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Forensic Analysis): 
1000

Lead/Senior Planning Engineer, CDM Smith, Abu Hamour (Musaimeer) Surface & Ground water Drainage Tunnel Phase 1

START Date: 
January, 2015
END Date: 
August, 2016

The project involves design and construction of 9.5 kilometres long and 3.7 meters pre-cast segment lined inside diameter, storm water conveyance tunnel. The project also includes 24 deep access shafts and their adit-tunnel connections for Qatar Public Work Authority (ASHGHAL).

Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Forensic Analysis): 
1000

Framework Coordinator = Senior Planning Engineer, ASCO Consulting Engineers/CDM Smith, Abu Hamour (Musaimeer) Surface & Ground water Drainage Tunnel Phase 1,

START Date: 
January, 2015
The project involves design and construction of 9.5 kilometres long and 3.7 meters pre-cast segment lined inside diameter, storm water conveyance tunnel. The project also includes 24 deep access shafts and their adit-tunnel connections for Qatar Public Work Authority (ASHGHAL).
Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Forensic Analysis): 
1000

Senior Planner / Senior Planning Engineer, KEO INTERNATIONAL CONSULTANT, Hamad Medical City Hospital Fit-Out

START Date: 
December, 2010

Delay Analysis / Time Impact Analysis / EOT Claims

Coordination of Contractors Programmes

Monitor Project Works to ensure Completion of Target Dates

Revise, Review and Show effects of Progress

Liaisons and coordination with Client, Contractors, Operators, End Users

Experience Hours (Planning & Scheduling): 
16000
Experience Hours (Cost Management): 
8000
Experience Hours (Forensic Analysis): 
2000

Market Place

See how the TIME - LOCATION - VIEW brings clearness to your work programmes