Planning Engineer, Al Habtoor Engineering LLC, Several Projects

START Date: 
January, 1999
END Date: 
May, 2003

Planning Engineer :Doing Labour Costing for this project. Analyzing the effect of Labour Cost with the forecast and actual and reporting it to the project director weekly along with different histograms of manpower, steel and concrete. Updating a database prepared myself using MS Access to control the delivery of Concrete, Reinforcement and Precast. Using this report to compare the original invoice submitting from the sub-contractor for the preparation of Monthly Invoice.

Project Controls Engineer, Iberdrola Engineering&Construction, Several Projects

START Date: 
August, 2003
END Date: 
May, 2005

Project Controls Engineer. Main projects and functions:

 CCGT Castellón 4 (850 MW, €350 M): Project Controls Engineer.

 BCC Tunisia (T&D, €30 M): Project Controls Engineer based in Tunis.

CCGT Santurtzi (400 MW, €200 M): Owner Cost Control Engineer.

Schedule preparation  or Thermal Generation Power Plants proposals.

Project Controls (Budget/Schedule Engineer), Tefirom Group, Several Projects

START Date: 
April, 2011
END Date: 
September, 2011

- Take active role in tender stages of upcoming projects, analyzing the work schedule and technical details from a financial and commercial perspective, creating a budget plan which is dependent to duration and fiction of each single project.

- Analyzing the annual budget study and to determine if it is realistic, complete and cost-effective,

- Recommend on how the budget study could be improved to minimize waste and maximize efficiency,

Project Controls (Budget/Schedule Engineer), Tefirom Group, Several Projects

START Date: 
April, 2011
END Date: 
September, 2011

- Take active role in tender stages of upcoming projects, analyzing the work schedule and technical details from a financial and commercial perspective, creating a budget plan which is dependent to duration and fiction of each single project.

- Analyzing the annual budget study and to determine if it is realistic, complete and cost-effective,

- Recommend on how the budget study could be improved to minimize waste and maximize efficiency,

Master Program Scheduler / Sr. Project Controls Eng. / Manager, DATSU Unlimited, Several Projects

START Date: 
March, 1991

Senior Project controlsa Specialist in charge of all etimating, planning, Scheduling, Tracking progress, costs and performances, invoicing , change managenent and post mortem reporting + lessons learned sessions.

Experience Hours (Planning & Scheduling): 
24000
Experience Hours (Cost Management): 
14000
Experience Hours (Forensic Analysis): 
10000