Sasol FTWEP – Wax Expansion Project

Senior Project Planner, Fluor, Sasol FTWEP – Wax Expansion Project

START Date: 
January, 2013
END Date: 
February, 2014
Develop, resource, baseline and update project schedule. Develop basis of schedule document. Setup and update monthly and weekly project progress reports. Level 4 construction planning and progress reporting. Setup and update detailed piping progress tracking sheets, daily progress reports and 2 week look ahead schedules. Liaise with sub-contractors for weekly progress reports. Liaise with client for revised access dates and information required by dates.