Petro Canada RCP Project

Lead Planner, Bantrel Company, Petro Canada RCP Project

START Date: 
November, 2005
END Date: 
February, 2007

Project: The Petro Canada Refinery Conversion Project

Project: $1.2B Engineering, Procurement and Construction to upgrade and refine oil sands bitumen. Client was Petro Canada. When I left Bantrel We were 80% complete, responsible for 3 out of 5 Silos.

Experience Hours (Planning & Scheduling): 
1200
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
400