Incheon Airport Railway Project

Consortium Planning Manager, Alstom Transport System Solutions, Incheon Airport Railway Project

START Date: 
January, 2006
END Date: 
July, 2007
  • Overall responsibility for planning and scheduling controls for the Electromechanical scope of the Incheon International Airport Railway Project (South Korea)
  • Monitored and controlled the integrated system schedule through the installation, test & commissioning, and closure phases
  • Prepared and issued weekly and monthly reports to project management and the Client
  • Desig

Planning Manager, ALSTOM Transport, Incheon Airport Railway Project

START Date: 
August, 2008
END Date: 
September, 2010

Incheon Airport Railroad Project, Korea

Developed Programme/Schedule:
Baseline Contract Schedule (Primavera P3)
Progress Monitoring Tools for Manufacturing & Delivery (Excel)
Progress Monitoring Tools for Installation (Excel)
Track Related Installation Programme (Excel)
Test and Commissioning Schedule (Primavera P3 & Excel)

Reporting:
Monthly Progress Report
Monthly Progress Presentation
Weekly Progress Report
Critical Path Analysis