  • Overall responsibility for planning and scheduling controls for the Electromechanical scope of the Incheon International Airport Railway Project (South Korea)
  • Monitored and controlled the integrated system schedule through the installation, test & commissioning, and closure phases
  • Prepared and issued weekly and monthly reports to project management and the Client
  • Designed and implemented specific progress measurement tools
  • Reviewed and developed the integrated schedule for the second phase of the project
  • Coached a local planner