Construction Project Planner / Senior Planner, MIV CONSTRUCTION, 4 Lane Road Project

START Date: 
May, 2015

by TermBlazer"> JobPurpose: 
-Meet Zamil Group obligations to clients with respect to delivery and construction of the project as per signed contract. 
-Prepare general planning schedule encompassing cost, resources, engineering, and construction sequence. 

Experience Hours (Planning & Scheduling): 
100
Experience Hours (Cost Management): 
300
Experience Hours (Forensic Analysis): 
100

Construction Project Planner / Senior Planner, agcc gulf, 4 Lane Road Project

START Date: 
May, 2015

Job Purpose: 
-Meet Zamil Group obligations to clients with respect to delivery and construction of the project as per signed contract. 
-Prepare general planning schedule encompassing cost, resources, engineering, and construction sequence. 

Experience Hours (Planning & Scheduling): 
0
Experience Hours (Cost Management): 
300
Experience Hours (Forensic Analysis): 
100

Architectural Designer / CAD operator, SEL-TOMA Jv, 4 Lane Road Project

START Date: 
January, 2013

Drawing Detail Of a Road . Draw Cross Section, Plan , Profile ,Intersection etc With AutoCAD and Calculate the quantity of work done .

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content