Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

1)Water & Sewerage Pipelines 2) Buildings 3) Infrastructure

Engineer / Project Engineer, Jainco Buildcon Limited, 1)Water & Sewerage Pipelines 2) Buildings 3) Infrastructure

START Date: 
June, 2013
END Date: 
June, 2015
Assist to create a detailed work plan which identifies and sequences the activities needed to successfully complete the project. Assist to provide inputs to planning in terms of schedule of procurement & engineering, Project deliverables, and duration for different project activities, pre-commissioning & commissioning etc. Preparation of Gantt chart/Activity Chart and time to time up gradation to report site progress. Prepare the pre-start estimate for project work according to site condition/ parameters in consultation with Site In-charge. Assists in developing specific project codes of
Experience Hours (Planning & Scheduling): 
2900
Experience Hours (Cost Management): 
3200
Experience Hours (Forensic Analysis): 
0

Engineer / Project Engineer, Jainco Buildcon Limited, 1)Water & Sewerage Pipelines 2) Buildings 3) Infrastructure

START Date: 
June, 2013
END Date: 
June, 2015
Assist to create a detailed work plan which identifies and sequences the activities needed to successfully complete the project. Assist to provide inputs to planning in terms of schedule of procurement & engineering, Project deliverables, and duration for different project activities, pre-commissioning & commissioning etc. Preparation of Gantt chart/Activity Chart and time to time up gradation to report site progress. Prepare the pre-start estimate for project work according to site condition/ parameters in consultation with Site In-charge. Assists in developing specific project codes of
Experience Hours (Planning & Scheduling): 
2900
Experience Hours (Cost Management): 
3200
Experience Hours (Forensic Analysis): 
0

Engineer / Project Engineer, Jainco Buildcon Limited, 1)Water & Sewerage Pipelines 2) Buildings 3) Infrastructure

START Date: 
June, 2013
END Date: 
June, 2015
Assist to create a detailed work plan which identifies and sequences the activities needed to successfully complete the project. Assist to provide inputs to planning in terms of schedule of procurement & engineering, Project deliverables, and duration for different project activities, pre-commissioning & commissioning etc. Preparation of Gantt chart/Activity Chart and time to time up gradation to report site progress. Prepare the pre-start estimate for project work according to site condition/ parameters in consultation with Site In-charge. Assists in developing specific project codes of
Experience Hours (Planning & Scheduling): 
2900
Experience Hours (Cost Management): 
3200
Experience Hours (Forensic Analysis): 
0

Estimator, MGL Group, 1)Water & Sewerage Pipelines 2) Buildings 3) Infrastructure

START Date: 
April, 2015

Estimator - MGL Group - preparing and pricing a range of schemes ranging from £10k to £5m

Planning Engineer, Arsan Contracting Company, 1)Water & Sewerage Pipelines 2) Buildings 3) Infrastructure

START Date: 
November, 2011
Handling Teams for Planning and Monitoring & Controlling Process Groups. Determining appropriate Techniques, Logistics for material & Equipment. Performance Reporting as Earned Value, Variances and Performance Indices. Project Planning & Scheduling - Primavera, Ms Project, Suretrak. Procurement : Plan, Conduct, Administer & Close Procurement.

Planning Engineer, Arsan Contracting Company, 1)Water & Sewerage Pipelines 2) Buildings 3) Infrastructure

START Date: 
November, 2011
Handling Teams for Planning and Monitoring & Controlling Process Groups. Determining appropriate Techniques, Logistics for material & Equipment. Performance Reporting as Earned Value, Variances and Performance Indices. Project Planning & Scheduling - Primavera, Ms Project, Suretrak. Procurement : Plan, Conduct, Administer & Close Procurement.

Planning Engineer, Arsan Contracting Company, 1)Water & Sewerage Pipelines 2) Buildings 3) Infrastructure

START Date: 
November, 2011
Handling Teams for Planning and Monitoring & Controlling Process Groups. Determining appropriate Techniques, Logistics for material & Equipment. Performance Reporting as Earned Value, Variances and Performance Indices. Project Planning & Scheduling - Primavera, Ms Project, Suretrak. Procurement : Plan, Conduct, Administer & Close Procurement.

Planning Engineer, Arsan Contracting Company, 1)Water & Sewerage Pipelines 2) Buildings 3) Infrastructure

START Date: 
November, 2011

 

·         Handling Teams for Planning and Monitoring & Controlling Process Groups.

·         Determining appropriate Techniques, Logistics for material & Equipment.

·         Performance Reportingas Earned Value, Variances and Performance Indices.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content