Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Manager Planning

Manager Planning, Shapoorji Pallonji & Co.Ltd, Hyderabad, Andhra Pradesh, India, Project handled - Construction of prestigious IT corridor for Wave-Rock Project with 5-levels of car parking (Green Building concept) Construction of 5 no’s of H1 Residential

START Date: 
July, 2008
END Date: 
October, 2009
Department: Planning and Site Monitoring Project handled - Construction of prestigious IT corridor for Wave-Rock Project with 5-levels of car parking (Green Building concept) - Hyderabad Client / Consultant - TSI Business Parks Pvt. Ltd. (U.S.A) Construction of 5 no’s of H1 Residential Apartments “THE EXCELSIOR” each apartment with 3-level basement and with 13 floor levels Boulder Hills EMAAR MGF, Hyderabad; Client / Consultant - EMAAR-MGF / Turner International
Experience Hours (Planning & Scheduling): 
2950
Experience Hours (Cost Management): 
2950
Experience Hours (Forensic Analysis): 
2950

Manager Planning, Shapoorji Pallonji & Co.Ltd, Hyderabad, Andhra Pradesh, India, Project handled - Construction of prestigious IT corridor for Wave-Rock Project with 5-levels of car parking (Green Building concept) Construction of 5 no’s of H1 Residential

START Date: 
July, 2008
END Date: 
October, 2009
Department: Planning and Site Monitoring Project handled - Construction of prestigious IT corridor for Wave-Rock Project with 5-levels of car parking (Green Building concept) - Hyderabad Client / Consultant - TSI Business Parks Pvt. Ltd. (U.S.A) Construction of 5 no’s of H1 Residential Apartments “THE EXCELSIOR” each apartment with 3-level basement and with 13 floor levels Boulder Hills EMAAR MGF, Hyderabad; Client / Consultant - EMAAR-MGF / Turner International
Experience Hours (Planning & Scheduling): 
2950
Experience Hours (Cost Management): 
2950
Experience Hours (Forensic Analysis): 
2950

Manager Planning, Shapoorji Pallonji & Co.Ltd, Hyderabad, Andhra Pradesh, India, Project handled - Construction of prestigious IT corridor for Wave-Rock Project with 5-levels of car parking (Green Building concept) Construction of 5 no’s of H1 Residential

START Date: 
July, 2008
END Date: 
October, 2009
Department: Planning and Site Monitoring Project handled - Construction of prestigious IT corridor for Wave-Rock Project with 5-levels of car parking (Green Building concept) - Hyderabad Client / Consultant - TSI Business Parks Pvt. Ltd. (U.S.A) Construction of 5 no’s of H1 Residential Apartments “THE EXCELSIOR” each apartment with 3-level basement and with 13 floor levels Boulder Hills EMAAR MGF, Hyderabad; Client / Consultant - EMAAR-MGF / Turner International
Experience Hours (Planning & Scheduling): 
2950
Experience Hours (Cost Management): 
2950
Experience Hours (Forensic Analysis): 
2950

Manager Planning, NESCOM, Research Projects

START Date: 
January, 2001
END Date: 
July, 2008
  • Responsible for planning of projects from level I to IV.
  • Responsible for implementation of Level IV plan at site.
  • Responsible for development of plant-wide master schedule including integration of engineering, procurement, maintenance, shutdown, and new construction schedules including critical path analysis using Primavera P3.
  • Prepare, implement and monitor the Work Breakdown Structure (WBS) for control and integrity. 
  • Development and baseline management of multiple project schedules.
  • Development of layouts and reports based on client and p

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.