Leighton Contractors (Asia) Limited

Project Planning Manager, Leighton Contractors (Asia) Limited, Culture Centre and Columbarium

START Date: 
June, 2016

Responsible for:

- Establish different levels of details for baseline programme

- Coordinated design deliverable schedule with designer

Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
1500

Project Planning Manager, Leighton Contractors (Asia) Limited, City of Dream Macau, North Lantau Hospital, Theatre, Culture Centre

START Date: 
January, 2009
END Date: 
June, 2016

Responsible for:

- Establish different levels of details for baseline programme

- Coordinated design deliverable schedule with designer

Experience Hours (Planning & Scheduling): 
16000
Experience Hours (Cost Management): 
9900
Experience Hours (Forensic Analysis): 
9000

Planning Engineer, Leighton Contractors (Asia) Limited, Seg.8.1 North Luzon Expressway Project

START Date: 
April, 2009
END Date: 
June, 2010

Construction of North Luzon Expressway Connecting Mindanao Avenue and Existing NLEX. Contract including construction of 2 bridges, toll plaza, clover lift (8 ramps), Drainage and Slope Protection Structures and Employers Representative Building Structures. It's a great challenge in the part of the contractor to build an expressway in the Highly Urbanized City of Manila, however, due to good management and operations experience the project was delivered on time.

 Engage in projects tender, coordinate with engineering manager in establishing working construction methodology.

Planning Engineer, Leighton Contractors (Asia) Limited, Gold Processing Plant Project

START Date: 
January, 2008
END Date: 
March, 2009

An EPC Contract of Accommodation Buildings (23 no.) and Gold Processing Plant. Gold Processing Plant comprising of 8 Leach Tanks 18m in diameter, Primary Crusher complete with mechanical and controls equipment, Structural Conveyors, Tailings Pond, Surge Bin, 2 Ball Mills, 1 Sag Mill and Gold room.

 Establish Detailed Contract, Working and Look Ahead Programmes.
 Prepare Progress Report S-Curve/Histogram/Gant Chart and developing Weekly, Monthly Progress Report, Recovery Plan and Look Ahead Programs.
 Provide Materials Take-off (MTO).

Stefan Jeffery

First Name: 
Stefan
Last Name: 
Jeffery
Professional Since: 
Oct-1996 (27.5 yrs experience)
Oldest experience: 
Jun 1994 (29.9 yrs experience, WARNING: 2.4 years variance with Professional Since)
Years Experience: 
41

Lead planner / Planning Manager, Leighton Contractors (Asia) Limited, XRL Contract C822

START Date: 
June, 1994

Responsible for the planning, programming and project controls on C822 in addition to delegating work to my 2 senior planners.