Revision of Schedule Performance Index from Tue, 2009-02-03 06:56

A parameter of Earned Value Analysis. The ratio of actual performance to planned performance. A ratio of less than 1 indicates the project is performing less than planned (that is, it is behind programme), a ratio of greater than 1 indicates the project is performing better than planned (that is, it is ahead of programme).