Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Area Planning Manager, CEGELEC (VINCI), Power Generation

START Date: 
September, 2013
END Date: 
July, 2014

-        Develop and maintain master baseline schedule

-        Set up  Project Control procedures

-        Set up Progress measurement system

-        Schedule update in weekly and monthly basis

-        Change Management (related to Planning & Schedule)

-        Project reporting

-        Forecasting (related to Planning & Schedule)

-        Develop detailed planning regarding construction activities

-        Develop manpower loading and man-hours S curves for construction

Experience Hours (Planning & Scheduling): 
1600
Experience Hours (Forensic Analysis): 
400