Senior Planning Engineer, Larsen & Toubro (L & T) Limited, SADARA Poly Ethylene

START Date: 
March, 2011
END Date: 
June, 2013

 

·            Creating & Maintaining a Schedule model to reflect realistic progress of the Project

·            Developed Primavera Schedule with resource (Labor & Material) loading, leveling to calculate manpower & material requirement in time phase in concern with Engineering, Procurement and Construction Team

·            Executing earned value management to measure the progress of project

·            Creating & analyzing Estimate to Complete (ETC) and Estimate at Completion (EAC) and Project Profitability, Project Schedule Preparation & Checking (level -1 to 4)

·            Performing Delay Analysis and Float Analysis using Primavera 6

·            Preparation of S-Curves, Bar Charts, Resource Histograms, WBS and Network Diagrams of the activities logic

·            Development of Reporting system & Master Project Schedule from scratch (L0 to L4)

·            Preparation of Invoices & subcontractor performance Measurements

·            Updating, Rescheduling & setting targets in all disciplines using PRIMAVERA V8,3

·            Harmonizing work between Engineering, Procurement & Construction by interfacing

         at critical points with client.

·            Preparation of all Management & Key stakeholders presentation

·            Analyzing schedule periodically using Monte-Carlo Analysis for Risk Mitigation using ORACLE

PERTMASTER (Risk Management Software) to apply contingency reserve

Experience Hours (Planning & Scheduling): 
4500
Experience Hours (Cost Management): 
4000
Experience Hours (Forensic Analysis): 
3500