Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Planner / Scheduler, Modern Tasami Contracting Co Jubail Saudi Arabia, 5 No Schools, Sewerage system, Water supply

START Date: 
April, 2012

Employment history

Modern Tasami Contracting Co Jubail Saudi Arabia   Feb 2012– Jun 2013

Planner / Scheduler                         

Major Projects

Construction of 5 No Schools,

Jubail , Saudi Arabia

 - SR 95,000,000 project.  Construction of 5 No Schools including site development works consisting roads, water supply, sewerage system, parking shade, boundary wall.

Rehabilitation  of  37 No Schools,

Jubail , Saudi Arabia

 - SR 45,000,000  project.  Construction for expansion of school buildings including site development works running tracks, roads, water supply, sewerage system, parking shade, boundary wall.

 

Planning/ Scheduling Responsibilities:

n  Created work breakdown structure (WBS) and developed and maintained  schedules by communication with the relevant Project Team using Primavera P6

n  Prepared the project engineering Schedules forlarge & small EPC projects .

n  Identifying critical paths for the project using critical path method

n  Monitored the schedule for all phases of the project, analysing deviations from the planned, analysing deviations impact and recommending corrective actions

n  Worked closely with all engineering and progress disciplines in order to take their buy-in for the project reports

n  Prepared schedule progress reports bi weekly and uploaded the budgeted man hours to P6 to have better track of the budget.

n  Reviewed the logic of the activities in P6 and making sure that these logics are correct as per Single Deliverable Flow Chart (SDFC)

n  Prepared cost reports which reflected committed cost, incurred cost, estimate to complete, budget at completion and estimate at completion.

n  Updated the milestone chart bi weekly and compared it with the baseline and last month to have better track of the milestone target dates

n  Participated in HAZOP and Model Reviews

n  Investigated schedule and cost issues, their impact on project and coordinated it with the project leads and PM to take decision on time

n  Coordinated with accounting and finance sections regarding invoice payments

n  Performed Earned Value Analysis and presenting data to the project manager and client in terms of CPI (Cost Performance Index) and SPI (Schedule Performance Index)

Green Top International Co. Doha, Qatar            Jul 2008 – Jan 2012

Project Planner                                               

Major Projects

Construction of 400/220/66 KV GIS Umm al Amad Super Substation (Qatar Power Transmission   System Expansion Phase –VIII),

Doha , Qatar

 - QR 110,000,000 project.  Construction of 400 KV substation GIS building , Control Room , LV/AC , Pump House  including site development works consisting  of roads , water supply , sewerage system , parking shade , boundary wall .

Refurbishment 132 KV GIS Doha South Super Substation (Qatar Power Transmission   System Expansion Phase –IX)

Doha , Qatar

 - SR 45,000,000 project.  Construction of 220/132 KV substation GIS building , Control Room , LV/AC  Pump House  including High / Low Voltage Cable Trenches and  site development works consisting  of roads , water supply , sewerage system , parking shade , boundary wall .

 

Planning/ Scheduling Responsibilities:

n  Developed schedules for engineering, procurement and construction activities by communicating with relevant discipline leads .

n  Attended public meeting, council and related meetings and assisted in the presentation of project information

n  Conducted inquiries in order to obtain necessary project construction information to address the contractors concerns and needs

n  Inspected activities during construction, prepared punch lists which described work to be done and helped in material requirement calculations

n  Prepared change order documents and processed it as agreed upon processing standards

n  Reviewed the contractor requests for scheduling extensions

n  Reviewed engineering drawings and specifications thoroughly resulted in less changes and saved time and cost for the project

n  Attended pre tender meeting and coordinated the contractor’s queries and concerns with the project team to answer their questions on time

Water and Power Development Authority, I.bad PakistanApr 2006– Jul 2008

Planning Engineer                                           

Major Projects

Construction of  Cat III , IV and V residences in 500 KV Grid Station Rawat and University Grid Station. Islamabad Pakistan

Construction of  Roads  in 500 KV Grid Stations Rawat , Islamabad  Pakistan .

 

 

National Transmission Desptach Co. I.bad Pakistan           Mar 2000 – Apr 2006

Project Engineer                                 

Major Projects

Rehabilitation of 500 KV transmission lines for Islamabad –Lahore section for repair of vulnerable towers.

Construction of approach and colony roads -220 KV grid station Burhan.

 

 

Hydro Electric Planning Organization (HEPO) Pakistan             Apr 1992– Mar 2000

                   Project Coordinator/ Scheduler                                   

Projects:             i) Construction of residences in  500 KV Sheikh   Muhammadi Grid Station Peshawar.

                            ii) Topographic and mapping works for hydro-power projects

National Transport Research Center Islamabad Pakistan      May 1991 – Mar 1992

                   Material Engineer                              

Project:              i) Laboratory testing for road division

Hussaini Construction Company, Rahim Yar Khan, Pakistan    Aug 1989– May 1991

                   Site engineer                             

Project:              i) Construction of surface and subsurface drains for control of water-logged area