Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Project Planner, SITEI Srl, Madinaty City Project

START Date: 
August, 2009
END Date: 
July, 2010

Development of the project baseline schedules, progress reports, an interim statement of payment, cost control, cash flow, document control, quantity survey, contract management, claims

Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
500