Cutover & Planning Manager, THALES , LUL Connect Project

START Date: 
January, 2005
END Date: 
September, 2005

 

Cutover & Planning Manager 2005 – 2005 (Planning software P3e V5)            

Thales Telecommunication Services Ltd, London

Working on the Connect Project – upgrading London Undergrounds communications network Fibre, Copper, Cab to shore.

Producing of cutover philosophy detailing all process and procedures that enable a safe introduction of the new system.

Creation of detailed plan for the cutover of service from old to new system.

Liaise with sub-contractors to ensure plans meet overall program of works

Ensure that the department & company do not delay the implementation of the project.

Ensure cutover plans are in compliance with project contracts.

Produce detailed financial & resources forecast to cover projects

Ensure all plans finances and resources are within the budget target