Senior Planning Engineer, AMEC, GDF Cygnus Development Project

START Date: 
January, 2012
END Date: 
January, 2014

Senior Planning Engineer GDF Cygnus Development Project, four topside modules with a combined tonnage totalling 13,200, Alpha complex comprises of three bridge linked modules covering accommodation, production and wellhead facilities, satellite Bravo wellhead platform 7km from parent asset. Located in Farringdon, London during Detailed Design phase of project following successful FEED. Construction and maintenance of level 3 plan containing 9,000 activities with a 720,000 man-hour budget. Progress capture, entry and analysis, focus on management of change together with impact on scheduling