PLANNING ENGINEER, Barmac, PSL, Total Fina Elf, Elf Elgin-Franklin PUQ Platform Onshore Fabrication and Offshore Hook-up

START Date: 
March, 1999
END Date: 
August, 2001

Working on the Elf Elgin-Franklin PUQ Platform during the onshore construction phase at the BARMAC Nigg facility.  Reporting to ITS Project Manager and responsible for the scheduling of manpower and testing work scope in accordance with the construction and commissioning programmes. 

Moving onto the hook-up based offshore, commissioning and post start-up phases.  Additional offshore roles included liaising with beach support, co-ordinating personnel change outs and work rotas, up mans and down mans, POB monitoring and logistics.  Responsible for the update and administration of the WPS Jobcard system for all disciplines and work scope.  Preparation of weekly Hook-up and Commissioning progress reports.