Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Afcons Infrastructure Limited

gonapa madhu babu

First Name: 
gonapa madhu
Last Name: 
babu
Professional Since: 
Aug-2003 (20.7 yrs experience)
Oldest experience: 
Jun 2008 (15.8 yrs experience, WARNING: 4.8 years variance with Professional Since)
Years Experience: 
2

Neeraj Narayan

First Name: 
Neeraj
Last Name: 
Narayan
Professional Since: 
Oct-2008 (15.5 yrs experience)
Oldest experience: 
May 2003 (21.0 yrs experience, WARNING: 5.5 years variance with Professional Since)
Years Experience: 
7

Afcons Infrastructure Limited Planner

START Date: 
December, 2009
Current Role

Afcons Infrastructure Limited Assistant Planner

START Date: 
June, 2004
END Date: 
June, 2005
Asst. Planner; Moolchand Under-pass (New Delhi), Pune Fly Overs, PK Roads (Part of GQ Project; NHAI), TATA Coal Jetty (Mumbai), Nava-Sheva Pipe Line...

Afcons Infrastructure Limited Planning Manager

START Date: 
January, 2003
END Date: 
November, 2005
This company was involved in Construction of 7 Kms of Viaduct & Two Station Buildings for Delhi Mass Rail Transport System in New Delhi
Reporting to the Project Manager, I was responsible for the following

     Prepare the monthly programme updates for the project
     Tracking progress, man hours and cost as compared to original plan and co-ordinate the weekly, fortnightly and monthly reports to Engineer / Employer
     Raise monthly payment request / invoices to the Engineer / Employer

Trainee Civil Engineer, Afcons Infrastructure Limited, Tata Coal Berth, Trombay, Mumbai

START Date: 
September, 2005
END Date: 
June, 2006
  • Construction of Block Wall Jetty at Mumbai (Client: Tata Power Ltd, and Engineer: Tata Consulting Engineers) as a Trainee Engineer from September 2005 to July 2006:
    • To assist the Project Planning Engineer to develop the necessary

Afcons Infrastructure Limited Project Controls Engineer

START Date: 
November, 2002
END Date: 
July, 2004
M/S AFCONS INFRASTRUCTURE LIMITED - ISO 9001-2000 (Nov 2002 to Jul 2004)

Project: Construction of LNG Receiving Terminal Jetty, Surat, India
Construction of Tug Mooring Facilities, Surat, India

Project Cost: Rs. 250 Million

Owner: THE ROYAL DUTCH PETROLEUM AND SHELL GROUP OF COMPANIES LTD.

Management Contractor: SAIPEM s. a. LTD

Details of Major Projects involved in:

Afcons Infrastructure Limited Civil Engineer

START Date: 
May, 2002
END Date: 
June, 2004
Construction of High Block Building for ROP Project at B.A.R.C. & TARAPUR 3 & 4 Nuclear Power Plant,Tarapur, Mumbai
Client:       Bhabha Atomic Research Centre/NPCIL
Consultant     :      M/s Stup Consultant Pvt. Ltd. Mumbai
Responsibilities:
Work execution in accordance with contract document, specifications, approved procedures & as per schedule.
Supervision, administration, inspection & expediting the task in assigned orders.
Preparation of material takeoff.

Afcons Infrastructure Limited Planner

START Date: 
August, 2006
END Date: 
August, 2007
- Preparation of Contract Appreciation Document
- Preparation of General and Detailed Method Statement
- Preparation of Construction Schedule Using Primavera
- Preparation of Accelerated Program & Catch up Plan
- Preparation of Extension of Time Program
- Preparation of Cash Flow Curves
- Preparation of Resource Allocation & Leveling
- Preparation of Planned Vs Actual Progress Program
- Preparation of Impact Program
- Progress Monitoring of the Project at Head Office Level
- Coordination with the Design Team

Afcons Infrastructure Limited Planner

START Date: 
February, 2005
END Date: 
August, 2006
Project: Kol dam Hydro Power Project (800MW)

Structure: Desilting arrangement (Excavation thruogh drilling & blasting, RCC raft, Piers, weirs, RCC deck)