  • Streamlining Project work scope & establishing the scope matrix by organizing the project kickoff meeting with client.
  • Organizing one day planning meeting internally to discuss and to make a common understanding of various aspects of the project.
  • Structuring WBS either in EPC or Package basis with respect to client requirement.
  • Preparation & Finalization of Project Client contractual Level-2 Schedule based on contractual completion.
  • Preparation & Finalization of Project Internal monitoring level-4 schedule.
  • Identifying Contract Milestones and reporting project status to top management through milestone analysis chart.
  • Streamlining Critical Path of the project.
  • Establishing Project Progress Monitoring System (PPMS) (S-Curves) baseline in EPC basis and for over all project.
  • Preparation and submission of monthly progress report which includes updated Project Schedule along with backlog & look ahead analysis, Milestone chart, procurement schedule, S-Curves & Updated DDL.
  • Catch up / recover plans to suit current site status of project. Ensuring & reporting the proper flow of recover plan.
  • Conduct weekly & monthly review meeting with Project Engineering, Manufacturing, and Procurement and Construction team and ensure the deliverables are in line with the approved schedule requirements.
  • Monthly review meeting with customer.
  • Periodic review meeting with package vendors
Professional Since: 
Jul-2005 (18.8 yrs experience)
Oldest experience: 
Jul 2005 (18.8 yrs experience)
Years Experience: 
42

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.