Shutdown Vs EPC Schedule

1 reply [Last post]
M. Kamel Bessekri
User offline. Last seen 8 years 18 weeks ago. Offline
Joined: 2 Jul 2009
Posts: 27
Groups: None

 

Hi Guys,

I want to know your opinion about the workload´s difference   in the monitoring   of Planning  type  shutdown   compared  with EPC Planning.

 How oft in minimum must  a shutdown planning  be updated ?

Thanks

Kamel

Replies

Bernard Ertl
User offline. Last seen 9 years 20 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 757

Schedules for Shutdowns/Turnarounds/Outages should be updated at the end of every shift.  Management should have updated progress reports and field supervisors should have updated shift (or "look ahead") schedules before the start of the next shift.