Quick Risk Template - distributions

D
Dennis Hanks 👤 Member for 19 years 1 month

Thanks Andrew;



This is what I currently do - part of my standard view. I was hoping to eliminate the fill down step by making the default change in Quick Risk.

A
Andrew Podolny 👤 Member for 21 years 6 months

Hi Dennis.

There is workaround - add 2 columns into your Risk View:

1st from Risk Inputs group - Duration Distribution

2nd from Risk Inputs group - Use Duration Distribution



Assign the Trigen distribution to the topmost activity through the bottom panel - you’ll see the changes in the recently added columns. Use ’Fill Down’ feature to fill these 2 columns.



Regards,

Andrew