Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Milestones and Risk Distribution

4 replies [Last post]
MATHEW JOSEPH
User offline. Last seen 12 years 28 weeks ago. Offline
Joined: 12 Jul 2004
Posts: 19
Groups: None
When applying uniform risk to all schedule activities imported from P6;

1. What happens to milestone activties?

2. As there are no distributions applied to milestone activities, will they form part of risk analysis?

3. Are milestone activities going to be part of distribution graph?

Replies

MATHEW JOSEPH
User offline. Last seen 12 years 28 weeks ago. Offline
Joined: 12 Jul 2004
Posts: 19
Groups: None
Yes.

The three important milestones are:

Substantial Engg. Complete ---- Mechanical Completion (Last portion) ---- Facility Turnover.


So the above milestones should be considered sequential milestones.

Mike Testro
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Mathew

Welcome to Planning Planet.

These section milestones - are they linked to anything else in the schedule?

Best regards

Mike Testro
MATHEW JOSEPH
User offline. Last seen 12 years 28 weeks ago. Offline
Joined: 12 Jul 2004
Posts: 19
Groups: None
Thanks Gary.

I am using Pertmaster. The EPC schedule was imported from P6. There is a Key Milestones schedule section with milestones representing commencement / completion of phases
Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline
Mathew,

Which software are you using? The below answers are assuming Pertmaster:

1. Not a lot, other than they are impacted by risk & uncertainties applied to activities upstream of the milestone

2. Since milestones are zero duration, uniform uncertainty distributions will not be applied

3. Yes. They will be impacted by risks and uncertainties upstream, so you will still be able to report probability distribution of milestones.

Cheers,

G