Progress measurement Procedure

1 reply [Last post]
bryc ali
User offline. Last seen 1 week 6 hours ago. Offline
Joined: 3 Nov 2009
Posts: 39

Hi everybody,

During the etablishement of the contract who is responsible of the production of the Progress measurement Procedure, is it the planner ? or the project manager ?

Replies

Zoltan Palffy
User offline. Last seen 3 days 11 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2433
Groups: None

I think a lot of this is dependent on who put the schedule together and who is going to maintain this and update it. I do not think that the PM will be updating the schedule so it would be the planner.