Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

proper methodology for implementing weight of the items in EPC projects

1 reply [Last post]
Eslam El-Khoriby
User offline. Last seen 6 years 33 weeks ago. Offline
Joined: 30 Aug 2017
Posts: 4
Groups: None

Hi, hope everything is going well. i am working as a planning engineer in electrical substation in Egypt. For a while, I have been searching for a proper methodology in order to sustain a real weight of the items comparing to all of the project.

Most of the companies use cost basis methodology which shows no impact of the critical path and some use time basis methodology which shows no impact of the cost of the items.

The construction works is estimated by 60% of the project duration and has a cost near by 10% of the project total cost, but on the other hand, the electrical times such as the power transformer is estimated by 30% of the total cost of the project and takes only 10% of the total time.

If we went by the cost methodology, it would be unfair for the construction phase and if we went by the time methodology, it would not be fair for the electrical items.

a way to implement the cost and the time factors for the same item in the percentage of the weight regarding the total project shall be more than needed taking into consideration the critical path activities.

An expert judgment to find a proper, real, fair methodology will be more than welcomed.

Thanks in advance for your time.

Replies

Mike Testro
User offline. Last seen 5 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Eslam

Break the task down into segments that only require one trade linked FS and then there is no need for any weighting.

Best regards

Mike Testro