Reduce the Activity Duration (P6 7.0)

4 replies [Last post]
Juan Perez
User offline. Last seen 12 years 37 weeks ago. Offline
Joined: 30 Sep 2012
Posts: 4
Groups: None

 

Hello Guys

As simple as this question may seem I’m new to Primavera P6.

I’m trying to add resources to an activity, to reduce the activity duration. For example, it takes 1 man 10 days to build a wall, however if I add another man to the activity (2 men) it would take only 5 days to build the wall.

The problem I’m incurring is that my activity duration is not reducing. I guess it a setting that needs to be changed, so could you kindly please advise where I’m going wrong.

Thank you

Replies

Juan Perez
User offline. Last seen 12 years 37 weeks ago. Offline
Joined: 30 Sep 2012
Posts: 4
Groups: None

Thank you Alexandre

I now understand

Regards

Juan Perez
User offline. Last seen 12 years 37 weeks ago. Offline
Joined: 30 Sep 2012
Posts: 4
Groups: None

 

Hello Usman,

Yes the Activity Type is: Resource Dependent and the Duration Type is: Fixed Units

usman arshad
User offline. Last seen 6 years 15 weeks ago. Offline
Joined: 19 Dec 2010
Posts: 10
Groups: None

did u check the activity is resource based?