Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Relationships in Gantt chart

2 replies [Last post]
Jean Desjardins
User offline. Last seen 8 years 4 weeks ago. Offline
Joined: 7 Nov 2011
Posts: 23
Groups: None

Hi,

The relationships in my Gantt Chart appear as linked to the baseline bars.

I would like to display the relationships linked to actual and remaining work bars.

May somebody help me with this ?

Thanks

Replies

Jean Desjardins
User offline. Last seen 8 years 4 weeks ago. Offline
Joined: 7 Nov 2011
Posts: 23
Groups: None

Thanks a lot Johannes its works !

Jean

Johannes Vandenberg
User offline. Last seen 5 weeks 5 days ago. Offline
Joined: 21 Jan 2010
Posts: 234

Hi Jean

Commen question in P6.

>> untick baseline bar from barview

or go to barview options and make sure that the remaining bar is below the bar that displays the basiline bar. This can be done with the arrows at the right hand side of the barview options screen.

Trust this helps