Question about leveling resources and durations

1 reply [Last post]
Scott Parker
User offline. Last seen 11 years 23 weeks ago. Offline
Joined: 26 Jul 2012
Posts: 6
Groups: None

I was wondering how to set my activities so that when I schedule and level my resources my durations change automatically?  I have been given the folowing information

 

Budgeted Hours for the activites

Available Manpower

Start date

Finish date

Set Calendar

 

I want to be able to play with my manpower and calendar to effect durations.  Hope this makes sence to someone.

 

Scott

Replies

SM PUM
User offline. Last seen 10 years 9 weeks ago. Offline
Joined: 15 Nov 2011
Posts: 77
Groups: None

In resource levelling Option "CHeck Off" Preserve schedule Early & Late Dates.

regards