Question about report

1 reply [Last post]
Scott Parker
User offline. Last seen 12 years 42 weeks ago. Offline
Joined: 26 Jul 2012
Posts: 6
Groups: None

My client wants me to submit a three week look ahead using the following format.  I was wondering if anyone can help me create it in P6.  Thank you in advance

 

Sample Report

 

Replies

Gary Whitehead
User offline. Last seen 6 years 13 weeks ago. Offline

You can'tcreate that in P6 -You can only display baseline/planned/actual dates in columns and not rows.

 

You'll have to export the data to excel, and then juggle it around into the right format.