Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Actual cost and Earned value cost

7 replies [Last post]
Kannan CP
User offline. Last seen 1 year 1 week ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi,

In my cost loaded schedule, the actual cost is showing some value higher than the earned value cost. So after each update to fix the problem, i make the actual cost similar to the earned value cost.

Is there any option to get the actual value similar to the earned value, based on the activity % progress.

Thanks in advance.

Regards

Kannan

Replies

Mohammed Azharuddin
User offline. Last seen 2 years 34 weeks ago. Offline
Joined: 17 Aug 2015
Posts: 11
Groups: None

Solved !

Check out my article here

https://www.linkedin.com/pulse/how-make-actual-value-equals-earned-cost-units-p6-using-azharuddin/?trackingId=07FcDenXTRe8sZHPAkEaJg%3D%3D

Mohammed Azharuddin
User offline. Last seen 2 years 34 weeks ago. Offline
Joined: 17 Aug 2015
Posts: 11
Groups: None

Solved !

Check out my article here

https://www.linkedin.com/pulse/how-make-actual-value-equals-earned-cost-units-p6-using-azharuddin/?trackingId=07FcDenXTRe8sZHPAkEaJg%3D%3D

Jenny Ingco
User offline. Last seen 3 years 41 weeks ago. Offline
Joined: 9 Jan 2012
Posts: 116

Kannan,

The Actual Cost= Invoices Paid+Invoices Acrrued - Disallowed Costs...

EV= % of the Total budgeted cost...

So, they both are diffrent values and can't be same.

 

Thank you,

 

HASAN

Raymund de Laza
User offline. Last seen 34 weeks 5 hours ago. Offline
Joined: 23 Nov 2009
Posts: 762

Anning,

It works....

 

1064
ev.jpg

Anning Sofi
User offline. Last seen 6 years 51 weeks ago. Offline
Joined: 22 Jan 2012
Posts: 89
Groups: None

 

That would be helpful to know there is a shorter way to have EV cost similar to actual cost.

As we all know,  EV cost is based on %performance complete x budget cost. Actual cost is calculated on %complete x budget, BUT in this case, %complete maybe based on units, physical or duration, depending on settings of the duration type for each activity. The % performance complete is not necessarily the same as the %complete based on units, physical or duration; hence the difference in values for EV and actual costs.

Raymund, Tools -> update progress may not work in the objective. Try it, as we had, and it didnt yield the same cost for EV and actual cost.

 

 

Raymund de Laza
User offline. Last seen 34 weeks 5 hours ago. Offline
Joined: 23 Nov 2009
Posts: 762

Kannan,

Use Tool... Update Progress.

Aldrin Morallos
User offline. Last seen 7 years 6 days ago. Offline
Joined: 1 Jun 2011
Posts: 5
Groups: None

Kannan,

For me, you cannot make the same result between Earned and Actual Value in P6 unless otherwise you formulate it.

 

Thanks.