Imported resources set to zero duration

R
Rob Kane 👤 Member for 22 years 4 months

Hi I have just imported some resources , I imported budget cost only. The problem is that all the resource durations have set themselves to zero and dates don't match activity dates. Any ideas on what setting I ma have wrong ?

Thanksb
Rob

J
Jenny Ingco 👤 Member for 14 years 5 months

Hi Rob,

Did you try to go Tools-Level Resources ? If not please, try to do it but, after you make a copy of your schedule and let me know if it's work with you?

 

Thank you,

 

HANSON

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts