Imported resources set to zero duration

1 reply [Last post]
Rob Kane
User offline. Last seen 3 years 24 weeks ago. Offline
Joined: 17 Jan 2004
Posts: 27
Groups: None
Hi I have just imported some resources , I imported budget cost only. The problem is that all the resource durations have set themselves to zero and dates don't match activity dates. Any ideas on what setting I ma have wrong ? Thanksb Rob

Replies

Jenny Ingco
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 9 Jan 2012
Posts: 116

Hi Rob,

Did you try to go Tools-Level Resources ? If not please, try to do it but, after you make a copy of your schedule and let me know if it's work with you?

 

Thank you,

 

HANSON