How to Update Primavera Schedule with Actuals

3 replies [Last post]
gaurav singh
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 2 Sep 2011
Posts: 8

Please help me!!

Could anyone tell me step wise step procedure to update primavera schedule with actual dates on monthly basis

Replies

gaurav singh
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 2 Sep 2011
Posts: 8

Actually I am updating my project on the basis of dates but for the activities which were sheuled to be start but not started as per data date how to update those activities so that our critical path won't change.?????

\

gaurav singh
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 2 Sep 2011
Posts: 8

Actually I am updating my project on the basis of dates but for the activities which were sheuled to be start but not started as per data date how to update those activities so that our critical path won't change.?????

\

SM PUM
User offline. Last seen 11 years 16 weeks ago. Offline
Joined: 15 Nov 2011
Posts: 77
Groups: None

gaurav singh

What type of updation you are going to do?? Physical % or duration % or others?.Or you are asking about auto compute actuals?? is your program resource loaded?

 

Regards?