The issue is 2 default calendars are ticked. If I try to untick one the message we get is {One default value is required.} If we try to assign another calendar as default the event code 2DVWV-3590-8 occurs. has any one experienced this?
P5 - Issue with 2 default calendars
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
The problem is in the database not in primavera.
Did you fixed it? Upgrading doesnt work :S
Richard,
You are trying to troubleshoot a problem on a really outdated piece of software. P5 is so old that I believe that Oracle/Primavera no longer supports it. Version 8 is the current version. I suggest that you ‘solve’ this problem by upgrading your software. There are literally hundreds of fixes and many good added features in the new software. Good luck!