Duration and time problem in P6 - Headache in P6

1 reply [Last post]
Haresh Jayanth
User offline. Last seen 6 years 9 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219

 

Dear All,

I have started my project on 24th July 2011 – 7:00 am and my completion date of project is 31st Dec 2012 5:00 pm. I am using 6 days 10 hours working calendar for all activities and my WBS is also using the same calendar as Default calendar. I noticed two problems in my program.

  1. Some of the activities are starting at 11:00 am , and some by 1:00pm , due to the reason if I give FS relation , then an activity instead of starting on next day , it start on the same day 11.00 am. How to solve this problem.
  2. The second problem is , if I assign duration of activities of 5 , P6 takes only 4. For example suppose I start and activity on 6th November 2011 (Sunday is working day) the activity should complete on 10th November 2011, but it is completion on 9th November 2011. The calendar I have already checked , that is not a problem , kindly explain.

Regards,

 

Haresh Jayanth

Replies

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

Haresh,

 

Go to Admin > Admin Preferences > Time Periods and check your Hours/Day setting is 10 instead of 8.