Difference Project Baseline and Primary Baseline

1 reply [Last post]
Muhammad Asim
User offline. Last seen 7 years 14 weeks ago. Offline
Joined: 5 Oct 2011
Posts: 22
Groups: None

Hi

What is difference between a Project baseline and a Primary baseline? Are the assigned seprately or together? When to assigne a Project baseline and when to Primary baseline?

Muhammad Asim

Replies

kumar s
User offline. Last seen 8 years 16 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 159

Dear,

Project baselines are default baselines which can be used as the initial baselline when you first start to update your project.
This baseline will apear by default in all the other users login also.you should always keep this as your baseline if you have only one baseline to maintain.

 

On the other hand primary/secondary/tertiary baselines can be considrered as user specific baselines.
these baselines are used where you will have to maintain 2 or more baselines for your comparision and analysis.
these user baselines will not appear in other users login when you are refering to the same project.

 