P6 - Additional 1 day duration

1 reply [Last post]
Ronn Chester Baluyot
User offline. Last seen 8 years 42 weeks ago. Offline
Joined: 28 Feb 2008
Posts: 33

In the programme I'm working using P6, I'm using "day" as the unit of time. I set Admin Preferences>Time periods to 24 Hours/Day. I did the same for the calendar. But for an activity with a 1 day duration, which will start on 08-Aug-11 00:00, it will be finished on 09-Aug-11 00:00. Actually it is the same for every activity of any duration. So if I will not show the time, if you look at the start and finis date, it is like having an additional 1-day for the duration. Anybody knows how to fixed this? I read some previous thread but I haven't found any solution. Thanks.

Replies

Mike Testro
User offline. Last seen 5 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Ronn

It is like a fence - the dates are the fence posts and the gaps is the duration - there is always 1 more fence post than gaps.

Maybe you can set your duration to 1 second before midnight - you can in Asta Powerproject.

Best regards

Mike Testro