Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Acknowledging the new dates after Resource Leveling

2 replies [Last post]
Ijaz Ahmad
User offline. Last seen 7 years 10 weeks ago. Offline
Joined: 11 Jul 2006
Posts: 42
Groups: None

Hello Guys,

I leveled the resources and the resource profile to me looks fine. I want to acknowledge the leveled dates but the problem is when I hit schedule, the dates go back to previous settings, even after I have unchecked the "Preserved scheduled early and late dates" option under level resources dialog box.

Any help will be highly appreciated.

Thanks

Ijaz

Replies

Satish Kumar
User offline. Last seen 7 years 6 weeks ago. Offline
Joined: 8 Feb 2010
Posts: 56

Hi

when you click the resource leveling icon There is a check box option in the pop up window which states to consider scheduling with resource leveling.

cheers

K