Oracle Primavera - PM6 Member for 15 years 6 months Member for 15 years 6 months Submitted by Rashid Iqbal on Thu, 2010-08-19 17:25 Permalink RE: Data label in resources graph I will suggest avoid making these graphs in P6..get the data in Excel and deal with it the way you feel like. Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Tue, 2010-08-17 06:05 Permalink RE: Data label in resources graph Fayas, Unfortunately that is not available in P6. You can add legend but not label for each time period. You can create a stacked histogram with legend if you wish. Log in or register to post comments
Member for 15 years 6 months Member for 15 years 6 months Submitted by Rashid Iqbal on Thu, 2010-08-19 17:25 Permalink RE: Data label in resources graph I will suggest avoid making these graphs in P6..get the data in Excel and deal with it the way you feel like.
Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Tue, 2010-08-17 06:05 Permalink RE: Data label in resources graph Fayas, Unfortunately that is not available in P6. You can add legend but not label for each time period. You can create a stacked histogram with legend if you wish.
Member for
15 years 6 monthsRE: Data label in resources graph
I will suggest avoid making these graphs in P6..get the data in Excel and deal with it the way you feel like.
Member for
19 yearsRE: Data label in resources graph
Fayas,
Unfortunately that is not available in P6. You can add legend but not label for each time period. You can create a stacked histogram with legend if you wish.