Data label in resources graph

Member for

15 years 6 months

I will suggest avoid making these graphs in P6..get the data in Excel and deal with it the way you feel like.


Member for

19 years

Fayas,

Unfortunately that is not available in P6. You can add legend but not label for each time period. You can create a stacked histogram with legend if you wish.