% complete type

2 replies [Last post]
kumar s
User offline. Last seen 8 years 17 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 159
dear guys,

i wanted to know
how to change the % complete type for all the acitivities at once.
i was able to change the duration type but the % complete type is not showing in the columns.
so where this can be changed......

thank you,

Replies

kumar s
User offline. Last seen 8 years 17 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 159
THANK YOU
Andrew Dick
User offline. Last seen 8 years 14 weeks ago. Offline
Joined: 14 Feb 2007
Posts: 295
Kumar,
The column is called ’percent complete type’.

You can do this through global change;
Where all of the following = ’Blank’, then ’Percent Complete Type’ = Duration, Physical or Units percent complete.

Andy