P6 version7 Baseline Error

2 replies [Last post]
Andy Dean
User offline. Last seen 10 years 41 weeks ago. Offline
Joined: 14 Aug 2009
Posts: 4
Groups: None
Hello

I have the following problem on P6 version7. Can anybody help please?:

When in project view and the project baseline is set to , the BL Project Total Cost shows £126,000 when closed and £6,383,000 when open.

Any Ideas why this is?

Many Thanks
Andy

Replies

Andy Dean
User offline. Last seen 10 years 41 weeks ago. Offline
Joined: 14 Aug 2009
Posts: 4
Groups: None
Rodel,
Many thanks for your quick response... and yes this has fixed it!

Cheers
Andy

Rodel Marasigan
User offline. Last seen 23 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Andy,
Project Window or View use summarized data and not Activity data. If you run Tools->Summarized-> Open Project or any of the three selections all freshly summarized projects will have fresh data from Activity Data.