(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

XER Import Error - Changing Version Not Working

6 replies [Last post]
Sonya Cortez
User offline. Last seen 35 weeks 6 days ago. Offline
Joined: 13 Nov 2017
Posts: 8
Groups: None

When attempting to import an XER from a new version of P6 to the 8.4 version I have, I get an error stating, "The import file is invalid."

I have already changed the version number in notepad. This trick only works sometimes when I import files from new versions of P6. I would ask the scheduler to send a saved down version of the file but our GCs aren't always accomodating. Are there any other tricks I can try when this occurs? 

 

UPDATE: I was not able to resolve this issue. However, by the mercy of my IT department, I was able to get an updated version of P6.

Replies

Zoltan Palffy
User offline. Last seen 22 hours 21 min ago. Offline
Joined: 13 Jul 2009
Posts: 2146

does the file now import into p6 with the new version number ?

Sonya Cortez
User offline. Last seen 35 weeks 6 days ago. Offline
Joined: 13 Nov 2017
Posts: 8
Groups: None

I am certain that I am not adding spaces.

Santosh Bhat
User offline. Last seen 1 hour 5 min ago. Offline
Joined: 15 Apr 2005
Posts: 156
Make sure you aren't introducing any more or less spaces when you replace the Release number with 8.4 This can be a reason why modifying the XER fails
Zoltan Palffy
User offline. Last seen 22 hours 21 min ago. Offline
Joined: 13 Jul 2009
Posts: 2146

maybe the file is bad 

Sonya Cortez
User offline. Last seen 35 weeks 6 days ago. Offline
Joined: 13 Nov 2017
Posts: 8
Groups: None
Just that the import is invalid.
Alexandre Faulx-B...
User offline. Last seen 2 hours 50 min ago. Offline
Joined: 20 Jan 2003
Posts: 1235

Sonya,

does the error message only say "the import is invalid", or is it descriptive?

Alexandre