Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Link to other files

3 replies [Last post]
Rifky Soedirdja
User offline. Last seen 7 years 50 weeks ago. Offline
Joined: 22 Apr 2010
Posts: 22
Hi,

I would like to check whether activity in my currect schedule has relationship with other files (i.e predecessors or successors). Is there any easy way to check it rather checking one by one? Thanks.

Rgds,

Rifky

Replies

Rodel Marasigan
User offline. Last seen 20 weeks 3 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Rifky,
I recommend modifying the activity id of your current schedule to have a different activity id from other files. You can use crtl+r (replace command) to change the beginning letter of activity id.
Ex below:
Replace Cmd
Make sure that the cursor is in activity id column then click replace all.
Now you can filter all predecessor begin with "A" if other files activity id start with "A".
Rifky Soedirdja
User offline. Last seen 7 years 50 weeks ago. Offline
Joined: 22 Apr 2010
Posts: 22
Rodel,

It happened when my boss asked me to do the simulation based on the latest information. So, I copied the file from the master file and made the simulation in my working folder, by adding more activities and changed some logic. Now, boss has agreed to use that "simulation" schedule and would like to integrate it into the master schedule.

My plan is to delete the OLD file from the master schedule and replace with the NEW one. The problem here is this OLD file has already some logic links to other files.
Based on your suggestion, I have to check and do the linking to my NEW file manually one by one, am I correct?

Please advise if what I did was correct and quite practical if I want to do the simulation in a separate file in the next future.

Thanks.

Rgds,

Rifky
Rodel Marasigan
User offline. Last seen 20 weeks 3 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Rifky,
If you use an intelligent Activity ID to each project to identify then you can use filter to predecessor or successor. If not and using same activity id then you have to do it manually.