Summary Schedule % Complete

4 replies [Last post]
Behnaz Soleimani
User offline. Last seen 14 years 22 weeks ago. Offline
Joined: 18 May 2010
Posts: 5
hello
a qusetion about Summary calculation for Schedule % Complete in P5?
what is the basis of calculation for summary schedule % Complete ?
thank you
Behnaz

Replies

V Kutty
User offline. Last seen 14 years 50 weeks ago. Offline
Joined: 7 Dec 2009
Posts: 11
Groups: None
Thanks, its been very useful.
Rodel Marasigan
User offline. Last seen 21 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Behnaz,
All cost will be calculated. If no cost but have resource unit only then it will not included in calculation. (i.e. resource without rate)
Behnaz Soleimani
User offline. Last seen 14 years 22 weeks ago. Offline
Joined: 18 May 2010
Posts: 5
thank you very much sir;
but when thsre is not any resource assign to activities, their schedule % Complete in summary calculated zero .
another question, when we have diffrent resource assign to activities,is it possible that it calculate Schedule % Compltet in summary base on specific one ( not all cudgeted cost, just for example for Labor unit cost)
thank you
Behnaz
Rodel Marasigan
User offline. Last seen 21 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Behnaz,
By default if not resource cost loaded a proportion of duration up to the data date. If resource loaded with cost a proportion of cost up to the data date.