FF with lag Relationship Issues
Forum Sponsor
Top Posters
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hunais M J
0 posts
Hi Mike and Sophia,
I usually avoid this problem (lags scheduling) by setting the default project calendar to (7 days) and changing the scheduling option for calculating lags to "schedule lags according to project’s default calendar"...
OR i use the option "24 hour calendar" but I ALWAYS make sure that my lags are multiplied by 3 (for shifts)...
Regards
Hi Sophia
This is the problem with SS Links plus lead lags - they should be avoided.
If you know why you need a 15 day lead lag then put in a relevant task and revert to FS links.
Lead lags take on the calendar of the upstream task so if you were thinking 15 calendar days the link will be 15 work days long.
Best regards
Mike Testro.